blank

Ayrshire College Dam Park

Despite a very tight 8-week window to work – the time in which there are no students attending Ayr College – Worksmart delivered another first-class project of approximately £600,000 at the Dam Park Building. The work involved a full strip-out and fast-track multi-trade refurbishment fit-out of 17,000sq ft, along with additional works to form the new care suites and music rooms. These new services all required power, lighting, ventilation and heating.

15 different trades were utilised for this project over the course of the 8 weeks and it was completed both on-time and budget, with no reportable incidents.

As there was a strict deadline for completion, works continued around the clock, with Worksmart working seven days a week from the beginning of the project and with extended daily working hours. Two different site managers worked the two main projects simultaneously, working together and having some fifty operatives on-site most weeks.

Client Testimonial

"“We have enjoyed working in partnership with Worksmart Contracts Ltd on these projects. The quality of works undertaken was excellent. The team were very professional and showed huge commitment to meeting the short timescale to support the student experience. The Worksmart team have created amazing learning and social spaces which will enhance the experiences of our students for years to come.”"

Heather Dunk

Ayrshire College Dam Park

Project Type:Fit-Out
Value:Approximately £600,000
Duration:8 weeks
Architect:Ayrshire College Direct for Architectural
Download Full Case Study